Construction Work – Sept. 30, ’26
These are the activities that were carried out today, Wednesday, as part of the construction of our school library.
The remaining 20 CHB (concrete hollow blocks) were laid. In addition, 4 concrete columns at the front of the building were poured.
Thanks to the great teamwork of the fathers who volunteered their time, once again under the supervision of Mr. Wilmer Pelaez, today’s planned work was completed ahead of schedule.
Tomorrow, the plan is to pour the 4 remaining concrete columns at the back of the building. The four columns poured today will now be given sufficient time to cure. The formwork used for these columns will be reused tomorrow for the remaining four columns.
Today, Stichting Ama Namin (SAN) did not need to provide lunch for the volunteers, as the planned work had already been completed by around 10:00 AM.
A heartfelt thank you to all our volunteers for their time, dedication, and great teamwork! ❤️🙏