Construction Update – July 21
Day 2
Construction continued at a steady pace. The window layout was marked out, making it clear where the windows will be installed, while the hollow block walls continued to rise. Little by little, the library is really starting to take shape.
Once again, many parents joined our own volunteers to lend a helping hand. Their dedication and commitment continue to demonstrate the strong community support behind this project.
Sir Antonio provided snacks and drinks to keep all the volunteers refreshed throughout the day. As on previous days, volunteer attendance and the completed work were carefully documented as a record of the community’s shared effort, commitment, and cooperation.